HFHS Mobile App, Project Status Tracker

Cross-Platform Mobile App (iOS + Android)  |  React Native + Expo  |  8-Week Build  |  Apr 6 - May 31, 2026  |  Status as of May 7, 2026

Total Deliverables
23
Completed
12 / 23
In Progress
4 / 23
Timeline
Apr 6 - May 31
Overall Status
Build Active
Delivered Completed as planned
In Progress Currently underway
Planned Not yet started
New Shipped in the last 2-3 weeks

Phase 1: Design & Architecture, Weeks 1-2, Apr 6 - Apr 19, 2026

6 of 6 Delivered
Week Deliverable Status
Wk 1 Mobile UX research and field technician workflow mapping Delivered
Wk 1 Define offline-first architecture (local SQLite + background sync to existing Supabase database) NewDelivered
Wk 1 Project scaffolding with React Native (Expo SDK), TypeScript, and shared component library setup for iOS + Android Delivered
Wk 2 Wireframes for all core screens (work orders, visit detail, photo upload, payments, schedule) Delivered
Wk 2 API contract definition (mobile app connects to the same Supabase REST APIs and Next.js endpoints built for the web platform) Delivered
Wk 2 Authentication flow design (shared Clerk instance with web platform, Expo SecureStore for token persistence) Delivered

Phase 2: Core Build, Weeks 3-6, Apr 20 - May 17, 2026

In Progress, 6 of 11 Delivered
Week Deliverable Status
Wk 3 Authentication module (Clerk Expo SDK, biometric unlock via expo-local-authentication, secure token storage) In Progress
Wk 3 Offline data layer (Expo SQLite for local storage, sync queue to Supabase, conflict resolution with server-wins strategy) NewDelivered
Wk 4 Work order list view with filters (assigned, in-progress, completed) Delivered
Wk 4 Work order detail screen (job info, member details, property history, checklist) Delivered
Wk 4 Download work orders for offline access Planned
Wk 5 Photo and document capture (expo-camera, expo-image-picker, multi-photo upload with compression to Supabase Storage) Delivered
Wk 5 Digital signature capture for service completion Planned
Wk 5 GPS check-in/check-out for visit tracking (expo-location, background location updates) Planned
Wk 6 Credit card payment processing (Stripe integration, on-site payments) Delivered
Wk 6 Push notifications via Expo Push Notifications (new assignments, schedule changes, urgent dispatches) Delivered
Wk 6 Background sync engine (expo-background-fetch, queue uploads when offline, sync to Supabase when connected) Planned

Phase 3: Testing, Polish & Launch, Weeks 7-8, May 18 - May 31, 2026

In Progress, 3 of 6 Started
Week Deliverable Status
Wk 7 End-to-end testing (all workflows, offline/online transitions) In Progress
Wk 7 Field testing with real technicians (beta group of 3-5 users) Planned
Wk 7 Performance optimization (app size, load times, battery usage) Planned
Wk 8 App store submission via EAS Build (iOS App Store + Google Play, single codebase for both platforms) In Progress
Wk 8 Technician training materials and quick-start guide In Progress
Wk 8 Production release and rollout to full team Planned