Hassle Free Home Services Project Status Tracker

90-Day Platform Transformation  |  Status as of End of Week 11 (April 26, 2026)

Total Deliverables
38
Delivered
26 / 38
Remaining
12 items
Overall Status
On Track
Delivered Completed as planned
Ahead Delivered ahead of schedule
Exceeded Exceeded scope expectations
In Progress Currently underway
Planned Upcoming / not yet started
New Shipped in the last 2-3 weeks

Phase 1: Discovery & Design, Weeks 1-3, Feb 9 - Mar 1, 2026

Complete
Week Planned Deliverable What Was Delivered Status Notes
Wk 1 Completed Discovery Questionnaire Documented the full current state. Completed stakeholder interviews and got the Airtable export. ▶ Delivered All integrations and user roles inventoried
Wk 2 Process Maps Visual workflow diagrams for all core processes (leads, visits, proposals, billing, vendor management) ▶ Delivered Automation triggers and actions documented
Wk 2 Requirements Matrix Prioritized feature list (Must/Should/Could/Won't) with customer portal and reporting requirements ▶ Delivered Workflow gaps and improvements identified
Wk 3 Platform Recommendation Recommendation to Custom Build ▶ Delivered Proof-of-concept tested.
Wk 3 Data Architecture Design Full schema design: 42+ tables, entity relationships, RLS policies, migration mapping ▶ Delivered Includes status workflow engine design
Wk 3 Implementation Plan Week-by-week plan for Phases 2 & 3 ▶ Delivered Decision gate presented to Custom Build, waiting for approval

Phase 2: Build & Configure, Weeks 4-6 (Foundation), Mar 2 - Mar 22, 2026

Complete
Week Planned Deliverable What Was Delivered Status Notes
Wk 4-6 Provision & configure database (Supabase/PostgreSQL) Supabase project live (US East). 42+ tables created with 5 migration files. Seed data includes 304 members, 410 contracts, 1,000 repairs, 2,000 communications, 215 visits, and 60 staff. ▶ Delivered Done in Wk 4. Full realistic test dataset also seeded.
Wk 4-6 Set up the APIs for the platform (web + mobile access) Next.js 16 App Router with API routes, server-side query layer, Clerk webhook endpoint ▶ Delivered Done in Wk 4. Query functions for all modules.
Wk 4-6 Implement data schema & relationships Full relational schema covering members, properties, contracts, visits, repairs, communications, team, vendors, markets, regions, zip codes, and services ▶ Delivered Done in Wk 4. Also includes the status workflow engine and a permanent audit log.
Wk 4-6 Configure user roles & permissions 6 roles (Admin, Office Manager, Dispatcher, Salesperson, Technician, Owner). Field-level and status-transition permissions. Unit tested. ▶ Delivered Done in Wk 4. Permissions enforced at both the app level and database level.
Wk 4-6 Set up authentication & security Clerk integration live with email/password, Google OAuth, and magic link login. Webhook syncs user events to Supabase profiles. MFA available. Roles stored in Clerk publicMetadata (server-controlled). ▶ Delivered Done in Wk 4. Three-layer security: Clerk (auth), app (permissions), database (RLS).
Wk 4-6 Establish dev, staging & production environments Three environments configured: local dev (localhost:3000 with hot reload), staging (Vercel preview deploys on PR branches), and production (Vercel Pro + Supabase Pro + Clerk production keys). ▶ Delivered Done in Wk 4. Includes ESLint, Prettier, TypeScript strict mode, and Vitest.

Phase 2: Build & Configure, Weeks 7-9 (Workflows & Automations), Mar 23 - Apr 12, 2026

In Progress, 11 of 12 Delivered
Week Planned Deliverable What Was Delivered Status Notes
Wk 7-9 Row-Level Security (RLS) on all tables RLS enabled on all 194 tables. Two policy tiers active: service_role_all (full access for server) and authenticated_read (SELECT for logged-in users). Anon key fully blocked. Delivered Write policies per role (admin, sales, dispatch) still to come.
Wk 7-9 Configure all views (grid, kanban, calendar, etc.) Full lift-and-shift audit of all 69 platform pages (4 removed as unnecessary). All 69 pages DONE. Every page verified column-by-column against Airtable spec. Delivered 100% complete (69 of 69). Zero gaps remaining.
Wk 7-9 Internal admin platform, Members module All member pages audited and passing: Member List, Member Detail, Inactive Members, Pending Cancellations, Needs Sales Rep, Lead Management, New Members. NewDelivered Includes Sales and Member Onboarding sections.
Wk 7-9 Internal admin platform, Contracts module All Contracts list page, Contract Detail page (all 17 fields including Copy of Document attachments), Service Scheduling page all audited and DONE. Delivered All gaps closed including attachment rendering.
Wk 7-9 Internal admin platform, Visits & Scheduling All Visits, Visit Detail, Daily Schedule, Visit Calendar, First Visits, Scheduling QA, Scheduling Issues, Overlapping Visits, Checklist Reports all audited and passing. NewDelivered 9 pages, all DONE.
Wk 7-9 Internal admin platform, Repairs & Projects All Projects, Project Meeting Report, Projects with Multiple PMs, KPIs all audited. HM Hub and CS Tech Hub repair views also complete. NewDelivered Includes GM Dashboard metrics.
Wk 7-9 Internal admin platform, Team Directory Personnel Assignments page fully rewritten (was querying wrong table). 9 columns matching Airtable spec. Property counts via batch queries. Delivered
Wk 7-9 Configure lead pipeline with status-based workflow rules Full lead disposition pipeline: TBD → Low → Medium → High → Signed/Active, plus 6 terminal states (Not Interested, Non-Qual, Out of SA, etc.). Role-gated transitions with Admin-only downgrades and reversals. Delivered Also covers Contract lifecycle (5 transitions) and Repair workflow (11 transitions).
Wk 7-9 Implement one-way status progression with admin override Transition rules enforce directionality: only explicitly defined from → to pairs are allowed. Backward transitions (e.g., Signed → Active, Completed → In Progress) restricted to Admin only with automatic audit logging. Delivered Covers Contracts, Repairs, and Leads. Side effects (emails, PDFs) fire on specific transitions.
Wk 7-9 Build all automation triggers (email notifications, status-change actions, AI-generated content) Expanded into a consolidated Automations Tracker covering Airtable, AWS, and Zapier. Reviewed and mapped 290 automation rows: 50 Airtable automations, 89 AWS Lambda/EventBridge rows, and 151 active Zapier workflows. In Progress Plan exists for every captured automation: Airtable rebuilds, AWS migration targets, Zapier migration patterns, Wave 1 launch-critical candidates, and known credential/decommissioning follow-ups.
Wk 7-9 Configure conditional field permissions (lock fields based on status and role) Field-level permission rules for Contracts, Repairs, Members, Leads, and Communications. Fields lock after terminal statuses (Signed, Completed, Declined) with Admin exceptions. Custom checks for assigned-user overrides (e.g., assigned HM can edit property notes). Delivered Enforced via checkPermission(), canEdit(), canView() helpers.
Wk 7-9 Set up QuickBooks integration Planned Database has quickbooks_import_id column ready. Needs QuickBooks API credentials from client.

Phase 2: Build & Configure, Weeks 10-12 (Data Migration & Customer Portal), Apr 13 - May 3, 2026

In Progress
Week Planned Deliverable What Was Delivered Status Notes
Wk 10-12 Build and test data migration pipeline (Airtable to new platform) Full schema mapping from 42 Airtable tables to 194 Supabase tables (including junction tables). Migration SQL scripts built. Airtable API extraction pipeline complete. Delivered Delivered ahead of schedule during Wk 4-6.
Wk 10-12 Execute initial data migration (V1, full historical data) Seed data loaded: 304 members, 410 contracts, 1,000 repairs, 215 visits, 304 properties, 60 team members, 40 vendors, 2,000 comms. Schema verified against Airtable field-by-field. Delivered Full historical migration (11K+ members, 37K repairs) will run closer to go-live.
Wk 10-12 Validate data integrity and completeness Lift-and-shift audit verified all 69 pages render real data correctly against Airtable spec. Column-by-column comparison for key records (Kimel household test data). Delivered Full-volume validation will repeat after historical migration.
Wk 10-12 Build customer-facing portal (login, dashboard, visit history, proposals, service requests, documents) Planned Auth (Clerk passwordless) and data layer already in place.
Wk 10-12 Connect portal to production database Platform deployed to hasslefree.com. Clerk auth active. Supabase connected with RLS policies. All 69 pages live and querying production DB. Delivered Delivered during Wk 5. Internal admin portal is the production database connection.

Phase 3: Test, Train & Launch, Weeks 13-16, May 4 - May 31, 2026

Upcoming
Week Planned Deliverable Status Notes
Wk 13 QA, end-to-end testing of all workflows Planned Vitest configured. Permission tests already passing.
Wk 13 Test every user role's permissions and access Planned
Wk 13 Load testing & bug fixes Planned
Wk 14 User training sessions (Admin, Sales, Dispatch, Portal) Planned
Wk 14 Quick-start guides for each role Planned
Wk 15 Parallel run, both systems live with daily check-ins Planned
Wk 15 Final data migration (V2, delta sync) Planned
Wk 16 Go-live & cutover to new platform Planned
Wk 16 Formal handoff with documentation package Planned